← All projects
Project 03 · Energy Infrastructure

Hidrosogamoso 820 MW Hydroelectric Power Plant

Energy InfrastructureEPCPower Generation
3 Francis type turbines
ISAGEN · National-scale energy
Hidrosogamoso 820 MW Hydroelectric Power Plant

Another coordination problem — at national scale.

01 · Objective

Bring 820 MW online — through construction, testing and pre-commissioning.

Participation in the construction, testing, pre-commissioning and project documentation control of the 820 MW Hidrosogamoso Hydroelectric Power Plant for ISAGEN.

CivilMechanicalElectricalInstrumentationControl
02 · How it started

A national-scale infrastructure project demanding rigorous traceability.

Context

Multi-year construction of one of Colombia's largest energy assets.

Need

Cross-discipline coordination to reach operational readiness.

Frame

Strict contractual, technical and operational requirements.

Aim

Documented, defensible path to commissioning.

03 · Scope & deliverables

Inspections, RFIs and a dossier the client could sign.

Scope of work
Field inspectionsTesting proceduresRFI managementStakeholder meetingsProgress reporting
Deliverables
Project dossierInspection recordsRFI logProgress reportsCommissioning support pack
Powerhouse interior
Spillway and outlet works
Felipe on site
04 · Team & my role

A coordination node across five disciplines.

Supported QA/QC and technical coordination — field inspections, testing procedures, documentation traceability, RFI management, stakeholder meetings, progress reporting and project dossier preparation.

05 · Process

From inspection plan to construction dossier.

  1. 01

    Coordinate testing and inspection activities across civil, mechanical, electrical and I&C.

  2. 02

    Manage RFIs end-to-end to keep execution aligned with the contractual baseline.

  3. 03

    Track progress and report deviations to stakeholders with clear evidence.

  4. 04

    Maintain documentation traceability across all disciplines and contractors.

  5. 05

    Compile and submit the construction dossier for client approval.

06 · Decision-making

Prioritize traceability. Resolve issues early.

Signal

Detected documentation gaps and discipline interface issues as soon as they appeared.

Action

Routed each issue to the right discipline with the right evidence, fast.

Trade-off

Invested time in documentation rigor to protect commissioning timeline.

Outcome

Less rework. A dossier the client could actually approve.

07 · Results & impact

A signed-off dossier on one of Colombia's largest energy projects.

0 MW
Installed capacity
       5
Disciplines coordinated
100%
Dossier approved

Contributed to the successful delivery and approval of the project construction dossier, ensuring compliance with contractual requirements, technical standards and operational readiness.

Next step

Have a project like this?